Key Installation Points

Following are the key components & labour that goes into an average bathroom installation:

  1. Initial Survey of Bathroom
  2. Submit detailed plan and quotation
  3. Ordering of materials from suppliers
  4. Delivery of materials to Gerlando showroom
  5. Delivery of materials to property
  6. Dust sheets to area of work and entrance to property
  7. Turn main stop tap
  8. Take out sink terminate and fit isolation valves
  9. Check if W.C. is the only one at property
  10. Take out W.C. and fit isolation valve
  11. Take out bath and fit isolation valve
  12. Take out radiator and fit islotation valve
  13. Remove all wall tiles
  14. Remove plaster from walls
  15. Ensure all pipes are covered to prevent debris damaging pipe work
  16. Plaster dab walls
  17. First fix shower
  18. First fix new pipe work
  19. Skim all joints
  20. Overboard ceiling
  21. First fix electrics
  22. Repair where necessary floors / floorboards
  23. Remove architrave or replace
  24. Allow new plasterwork to dry
  25. Fit laser level in preparation for tiling
  26. Fit starting bead
  27. Tile all walls using 2mm spacers
  28. Fit windows / corner beads
  29. Fit all tile cuts
  30. Allow tiling to dry for 24 hours
  31. Grout all tile joints
  32. Fit 2mm spacers
  33. Polish finished tiling
  34. Mount legs to bath
  35. Fit taps to bath
  36. Fit combination waist to bath
  37. Securely screw bath to wall, water tight seal with mildew resistant silicon
  38. Fit bath taps
  39. Plumb hot and cold feed to bath taps
  40. Fit waste 1.5" pipe to soil
  41. Mount taps to bath
  42. Fit waste to basin
  43. Fit basin to wall
  44. Fit pedestal to basin
  45. Plumb hot and cold to basin taps
  46. Fit 1.25" waste and trap to soil
  47. Mount cistern for W.C.
  48. Assemble W.C.
  49. Fit W.C. seat
  50. Fit multi quick to soil pipe
  51. Securely screw W.C. to floor and wall
  52. Electrically wire shower 6 - 10 mm cable
  53. Supply water feed to shower
  54. Fit shower and pull cord
  55. Fit extractor fan
  56. Fit 4 spot lights
  57. Lay water proof plywood to floor
  58. Tile floor using flexi grout
  59. Fit accessories - Toiler roll holder, tooth brush holder, soap dish, towel rail
  60. Plumb heating pipes
  61. Fit and plumb heated towel rail
  62. Fit radiator valves
  63. Fit bath screen over bath
  64. Clean and polish finished bathroom
  65. Silicon bath and basin